Reuters: Motiva to proceed with hydrocracker work

Published 3:30 pm Wednesday, September 14, 2016

Motiva Enterprises will proceed with a two-month overhaul of the hydrocracker at the Port Arthur refinery at the end of September, instead of postponing the work, sources familiar with the company’s plans said on Tuesday.

Motiva weighed putting off the overhaul of the 60,000 barrel-per-day hydrocracking unit at the 603,000 bpd Port Arthur refinery to make up for production lost after an early August fire idled the HCU at the company’s Convent, Louisiana, refinery, the sources told Reuters in August, according to Reuters.

The 45,000 bpd heavy oil hydrocracker at the 235,000 bpd Convent refinery is expected to return to partial production by the end of the year.

Subscribe to our free email newsletter

Get the latest news sent to your inbox